      • Ala Moana Wastewater Pump Station Force Mains #3 & #4
      • Pearl Harbor Channel Underwater Waterline Crossing
      • Kaneohe Bay Drive Trunk Sewer Reconstruction
      • Ford Island Waterline Replacement
      • FY01 MCON Project P-491
      • Long Range Sewer Rehabilitation
      • Kihei Effluent Reuse System
    • Past Projects
      • General Civil Projects
      • Wastewater Projects
      • Water Projects
    • Project Gallery
  • FAINC News
  • CONTACT

Project Gallery

ALA MOANA WASTEWATER PUMP STATION FORCE MAINS #3 AND #4

  • Ala Moana Force Mains #3 & #4 alignment and service area
  • The contractor chose to use a Vertical Shaft Sinking Machine (VSM) to construct the deep shafts on each side of Honolulu Harbor
  • Photo of the VSM before beginning construction of the deep shafts
  • Closeup of the VSM rotating cutting head
  • Construction of the ring beam around the shaft and the first shaft wall segment progressing
  • View from above of the VSM in the shaft
  • VSM rotating cutting head within the shaft. As excavation progresses, the shaft wall segments are constructed and lowered into the excavation.
  • Approximately 100’ deep shaft completed
  • 81” diameter steel casing pipe being lowered into the shaft
  • Microtunnel boring machine (MTBM) being prepared for launch
  • MTBM reaching receiving shaft
  • MTBM at receiving shaft
  • Steel casing pipe being jacked in behind the MTBM
  • 63” diameter fiberglass reinforced polymer mortar (FRPM) pipe installed within the steel casing pipe
  • Parallel 63” diameter FRPM pipe being installed by open excavation at the wastewater treatment plant
  • Valves and interconnections of the force mains at the pump station and treatment plant help to provide operational flexibility


MCKINLEY HIGH SCHOOL SYNTHETIC TRACK AND FIELD

  • McKinley High School logo on completed athletic field
  • Project site before construction start
  • Project site under construction
  • Project site upon completion
  • Perimeter fence to be replaced
  • New perimeter fence and landscaping installed
  • Tennis Courts under construction
  • Tennis Courts completed
  • Track sidewalk and fencing installation in progress
  • Track sidewalk, fencing and landscaping completed
  • Ewa end zone before construction start
  • Long Jump/Triple Jump & Pole Vault under construction
  • Long Jump/Triple Jump & Pole Vault under construction
  • Track paving in progress
  • Ewa end zone completed
  • Diamond Head end field subdrain installation
  • Track paving in progress
  • Synthetic track lift installation
  • Lane number installation
  • Athletic Field under construction
  • Athletic Field under construction
  • Athletic Field completed


PEARL HARBOR CHANNEL UNDERWATER WATERLINE CROSSING

  • Installation of a 24-in. DR 18 fusible PVC water transmission main via horizontal directional drilling (HDD)
    under the Pearl Harbor channel from Pearl City Peninsula to Ford Island
  • A pneumatic hammer (yellow arrow) used to drive the 48-in casing
    (each approximately 40 ft. long) into the ground
  • HDD entry pit showing 48-in casing and centralizer pipe
  • Fusible PVC pipe assembly on Ford Island
  • Pipe string in process of being pulled across Saratoga Blvd. in the northeast
    direction onto the Ford Island pitch and putt golf course (red arrow)
  • Tracked excavator being used to pull the drill string towards the HDD entry pit area next the Ford Island Brig
  • Shackle assembly and 24-in barrel reamer connected to the drilling rods at the Ford Island exit pit
  • Hookup of pipe string to drill rods complete as the pipe is raised into position
    to enable the string to enter the hole
  • Initial entry of pipe string into bored hole
  • The last 100 ft. of pipe string being pulled into the hole
  • 24-in barrel reamer (yellow arrow) and shackle assembly (red arrow) emerge
    from 48-in steel casing covered with drilling mud at Pearl City Peninsula
  • Pulling head on pipe string extending out of steel casing at Pearl Harbor Peninsula


KAMEHAMEHA SCHOOLS HAWAII CAMPUS – KAME’EIAMOKU BASEBALL FIELD IMPROVEMENTS

  • Baseball Field after logo installation
  • Baseball Field site
  • Baseball Field trenching for subdrains
  • Baseball Field subdrains installation
  • Baseball Field crushed rock base installation
  • Baseball Field crushed rock base installation
  • Baseball Field drain outlets installed
  • Baseball Field synthetic turf installation
  • Baseball Field terra cotta warning track installation
  • Baseball Field infield from home plate


KAMEHAMEHA SCHOOLS HAWAII CAMPUS – PAI’EA TRACK IMPROVEMENTS

  • Track repairs, striping and gravel border completed
  • Track full depth replacement areas fixed and awaiting top coat
  • Track full depth replacement areas fixed and awaiting top coat
  • Track event area with finished top coat
  • Track striping installation
  • Track striping installation


DIAMOND HEAD ROAD / MONSARRAT AVENUE / MAKAPUU AVENUE / 18TH AVENUE
BIKEWAY IMPROVEMENTS

  • Shared-use lane on Monsarrat Avenue from Poni Moi Street
  • Diamond Head Road bicycle lane symbol installation in progress
  • Diamond Head Road traffic control for bicycle lane striping and symbol installation
  • Diamond Head Road bicycle lane striping and symbol installation completed
  • Diamond Head Road bicycle lane guide line striping and symbol installation completed
  • Bicycle lane with signage on Diamond Head Road
  • Transition from bicycle lane to shared-use lane on Diamond Head Road
  • Bicycle lane with signage on 18th Avenue
  • Bicycle lane with signage on Makapuu Avenue
  • Shared-use lane with signage on Makapuu Avenue
  • Shared-use lane project start from Monsarrat Avenue
  • Shared-use lane with signage on Monsarrat Avenue
  • Shared-use lane on Monsarrat Avenue


KAMEHAMEHA SCHOOLS KAWAILOA AGRICULTURAL 6MG RESERVOIR

  • Completed new reservoir to right of old abandoned reservoir
  • Old reservoir and new reservoir site before construction
  • Earthwork in progress
  • Earthwork nearing completion
  • Earthwork and 2nd spillway before the liner installation. In the background is the reservoir intake structure.
  • 18" IPS HDPE installation
  • New 24" reservoir effluent line and the location to tap to the existing 24" line
  • Valve before the construction
  • Valve station after the construction
  • Primary spillway structure
  • Liner installation and inspection
  • The reservoir inlet structure
  • Before grassing
  • After grassing


KANEOHE ELEMENTARY SCHOOL SLOPE STABILIZATION

  • Completed wall and fence for slope stabilization project.
  • Existing fence and brush before project start.
  • Slope to be stabilized on other side of existing fence.
  • Excavation for wall footing.
  • Wall footing cement pour in progress.
  • Beginning of fenced slope area before project start.
  • Fence, wall and slope stabilization completed.
  • Top slope view of fence, wall and swale after project completion.