ALA MOANA WASTEWATER PUMP STATION FORCE MAINS #3 AND #4
- Ala Moana Force Mains #3 & #4 alignment and service area
- The contractor chose to use a Vertical Shaft Sinking Machine (VSM) to construct the deep shafts on each side of Honolulu Harbor
- Photo of the VSM before beginning construction of the deep shafts
- Closeup of the VSM rotating cutting head
- Construction of the ring beam around the shaft and the first shaft wall segment progressing
- View from above of the VSM in the shaft
- VSM rotating cutting head within the shaft. As excavation progresses, the shaft wall segments are constructed and lowered into the excavation.
- Approximately 100’ deep shaft completed
- 81” diameter steel casing pipe being lowered into the shaft
- Microtunnel boring machine (MTBM) being prepared for launch
- MTBM reaching receiving shaft
- MTBM at receiving shaft
- Steel casing pipe being jacked in behind the MTBM
- 63” diameter fiberglass reinforced polymer mortar (FRPM) pipe installed within the steel casing pipe
- Parallel 63” diameter FRPM pipe being installed by open excavation at the wastewater treatment plant
- Valves and interconnections of the force mains at the pump station and treatment plant help to provide operational flexibility
MCKINLEY HIGH SCHOOL SYNTHETIC TRACK AND FIELD
- McKinley High School logo on completed athletic field
- Project site before construction start
- Project site under construction
- Project site upon completion
- Perimeter fence to be replaced
- New perimeter fence and landscaping installed
- Tennis Courts under construction
- Tennis Courts completed
- Track sidewalk and fencing installation in progress
- Track sidewalk, fencing and landscaping completed
- Ewa end zone before construction start
- Long Jump/Triple Jump & Pole Vault under construction
- Long Jump/Triple Jump & Pole Vault under construction
- Track paving in progress
- Ewa end zone completed
- Diamond Head end field subdrain installation
- Track paving in progress
- Synthetic track lift installation
- Lane number installation
- Athletic Field under construction
- Athletic Field under construction
- Athletic Field completed
PEARL HARBOR CHANNEL UNDERWATER WATERLINE CROSSING
- Installation of a 24-in. DR 18 fusible PVC water transmission main via horizontal directional drilling (HDD)
under the Pearl Harbor channel from Pearl City Peninsula to Ford Island - A pneumatic hammer (yellow arrow) used to drive the 48-in casing
(each approximately 40 ft. long) into the ground - HDD entry pit showing 48-in casing and centralizer pipe
- Fusible PVC pipe assembly on Ford Island
- Pipe string in process of being pulled across Saratoga Blvd. in the northeast
direction onto the Ford Island pitch and putt golf course (red arrow) - Tracked excavator being used to pull the drill string towards the HDD entry pit area next the Ford Island Brig
- Shackle assembly and 24-in barrel reamer connected to the drilling rods at the Ford Island exit pit
- Hookup of pipe string to drill rods complete as the pipe is raised into position
to enable the string to enter the hole - Initial entry of pipe string into bored hole
- The last 100 ft. of pipe string being pulled into the hole
- 24-in barrel reamer (yellow arrow) and shackle assembly (red arrow) emerge
from 48-in steel casing covered with drilling mud at Pearl City Peninsula - Pulling head on pipe string extending out of steel casing at Pearl Harbor Peninsula
KAMEHAMEHA SCHOOLS HAWAII CAMPUS – KAME’EIAMOKU BASEBALL FIELD IMPROVEMENTS
- Baseball Field after logo installation
- Baseball Field site
- Baseball Field trenching for subdrains
- Baseball Field subdrains installation
- Baseball Field crushed rock base installation
- Baseball Field crushed rock base installation
- Baseball Field drain outlets installed
- Baseball Field synthetic turf installation
- Baseball Field terra cotta warning track installation
- Baseball Field infield from home plate
KAMEHAMEHA SCHOOLS HAWAII CAMPUS – PAI’EA TRACK IMPROVEMENTS
- Track repairs, striping and gravel border completed
- Track full depth replacement areas fixed and awaiting top coat
- Track full depth replacement areas fixed and awaiting top coat
- Track event area with finished top coat
- Track striping installation
- Track striping installation
DIAMOND HEAD ROAD / MONSARRAT AVENUE / MAKAPUU AVENUE / 18TH AVENUE
BIKEWAY IMPROVEMENTS
- Shared-use lane on Monsarrat Avenue from Poni Moi Street
- Diamond Head Road bicycle lane symbol installation in progress
- Diamond Head Road traffic control for bicycle lane striping and symbol installation
- Diamond Head Road bicycle lane striping and symbol installation completed
- Diamond Head Road bicycle lane guide line striping and symbol installation completed
- Bicycle lane with signage on Diamond Head Road
- Transition from bicycle lane to shared-use lane on Diamond Head Road
- Bicycle lane with signage on 18th Avenue
- Bicycle lane with signage on Makapuu Avenue
- Shared-use lane with signage on Makapuu Avenue
- Shared-use lane project start from Monsarrat Avenue
- Shared-use lane with signage on Monsarrat Avenue
- Shared-use lane on Monsarrat Avenue
KAMEHAMEHA SCHOOLS KAWAILOA AGRICULTURAL 6MG RESERVOIR
- Completed new reservoir to right of old abandoned reservoir
- Old reservoir and new reservoir site before construction
- Earthwork in progress
- Earthwork nearing completion
- Earthwork and 2nd spillway before the liner installation. In the background is the reservoir intake structure.
- 18" IPS HDPE installation
- New 24" reservoir effluent line and the location to tap to the existing 24" line
- Valve before the construction
- Valve station after the construction
- Primary spillway structure
- Liner installation and inspection
- The reservoir inlet structure
- Before grassing
- After grassing
KANEOHE ELEMENTARY SCHOOL SLOPE STABILIZATION
- Completed wall and fence for slope stabilization project.
- Existing fence and brush before project start.
- Slope to be stabilized on other side of existing fence.
- Excavation for wall footing.
- Wall footing cement pour in progress.
- Beginning of fenced slope area before project start.
- Fence, wall and slope stabilization completed.
- Top slope view of fence, wall and swale after project completion.